Borrow pits are generally provided
- AWhen earthwork in filling exceeds the earthwork in excavationCorrect
- BWhen earthwork in excavation exceeds the earthwork in filling
- CTo keep the saturation line within the dam section
- DTo increase discharge carrying capacity of a canal
Solution
Concept
Borrow pits in canal earthwork
Step-by-step solution
1. A borrow pit is an excavation made outside the canal section to obtain earth. 2. Earth is needed when the quantity of filling is more than the quantity of cutting. 3. So borrow pits are provided when earthwork in filling exceeds earthwork in excavation.
Explanation
In canal and embankment construction, the soil excavated is reused for banks. When the excavation is not enough to make the required fill, extra earth is taken from borrow pits. Spoil banks are the opposite: they are used when the excavation is more than the fill.
Shortcut
Fill > cut → Borrow pit. Cut > fill → Spoil bank.
Common mistake
Reversing borrow pit and spoil bank.
Correct answer: A) When earthwork in filling exceeds the earthwork in excavation