Q.26 Minimum shear reinforcement is provided in an RCC beam under which of the following conditions?
- ANominal shear stress is greater than design shear strength of concrete but less than maximum shear stress
- BNominal shear stress is less than design shear strength of concreteCorrect
- CNominal shear stress is greater than maximum shear stress
- DNominal shear stress is greater than design shear strength of concrete
Solution
Concept
As per IS 456, when the nominal shear stress τv is less than the design shear strength of concrete τc, only minimum shear reinforcement is provided.
Formula
τv = Vu/(b d); Asv/(b sv) ≥ 0.4/(0.87 fy)
Step-by-step solution
1. Find the nominal shear stress τv = Vu/(b d). 2. Compare τv with τc (from the table) and τc,max. 3. If τv < τc, provide minimum shear reinforcement. 4. If τc < τv < τc,max, design the shear reinforcement for Vus = Vu − τc b d. 5. If τv > τc,max, revise the section. 6. So minimum shear reinforcement applies when τv < τc.
Explanation
Concrete alone can carry the shear when τv is less than τc. Still, IS 456 asks for minimum stirrups to stop sudden brittle failure and to hold the main bars. This minimum steel is given by Asv/(b sv) ≥ 0.4/(0.87 fy).
Why the other options are wrong
A: In this range, designed shear reinforcement is needed, not just minimum steel. C: If τv exceeds τc,max, the section must be redesigned. D: If τv exceeds τc, designed shear reinforcement is needed.
Shortcut
τv < τc gives minimum stirrups. τc < τv < τc,max gives designed stirrups. τv > τc,max means revise the section.
Common mistake
Mixing up option A (design shear reinforcement) with the condition for minimum shear reinforcement.
Correct answer: B) Nominal shear stress is less than design shear strength of concrete