The unit of payment of cement concrete in lintel work is
- Aper m
- Bper m²
- Cper m³Correct
- DNone of the above
Solution
Concept
Unit of payment
Step-by-step solution
1. Cement concrete is measured and paid in cubic metres (m³).
Explanation
Concrete is a volume item.
Why the other options are wrong
Per m or per m² do not fit a concrete item.
Shortcut
Concrete = m³.
Correct answer: C) per m³