Under the LARR Act, consent is required from how much of the land owners in Public-Private Partnership (PPP) projects before acquisition?
- A50%
- B60%
- C70%Correct
- D80%
Solution
Concept
Consent requirements for land acquisition under the LARR Act vary based on whether the project is public, PPP-based, or private.
Step-by-step solution
1. Identify the project type given in the question: Public-Private Partnership (PPP) project. 2. Recall the statutory consent provisions under Section 2(2) of the LARR Act, 2013. 3. For PPP projects, prior consent from at least 70% of the affected land owners is mandatory. 4. Match with the given options to select option (C).
Explanation
According to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013, prior consent of at least 70% of affected land owners is required for land acquisition in Public-Private Partnership (PPP) projects. For private projects, the required consent is 80%.
Why the other options are wrong
A: 50% is incorrect and does not apply to any category under the LARR Act. B: 60% is not a statutory threshold under the LARR Act. D: 80% is the required consent percentage for private projects, not PPP projects.
Shortcut
Remember: PPP projects require 70% consent, while purely Private projects require 80% consent.
Common mistake
Confusing the 70% consent requirement for PPP projects with the 80% requirement for private companies.
Correct answer: C) 70%