A Gantt Chart indicates
- ABalance of work to be done
- BEfficiency of project work
- CComparison of actual process with the scheduled progressCorrect
- DProgress cost of Project
Solution
Concept
Gantt chart
Step-by-step solution
1. A Gantt (bar) chart shows planned and actual progress against time.
Explanation
It compares actual progress with the schedule.
Why the other options are wrong
It does not show cost or efficiency.
Shortcut
Gantt = planned vs actual.
Correct answer: C) Comparison of actual process with the scheduled progress