The entire process of a project may be considered to be made up of a number of sub processes placed in different stages called the
- ATechnical key resources
- BWork key structure
- CWork Breakdown Structure (WBS)Correct
- DNone of the above
Solution
Concept
WBS
Step-by-step solution
1. Dividing a project into sub-processes in stages is the Work Breakdown Structure.
Explanation
WBS breaks the project into manageable parts.
Why the other options are wrong
"Work key structure" and "technical key resources" are not terms.
Shortcut
WBS.
Correct answer: C) Work Breakdown Structure (WBS)