In PERT analysis, negative slack occurs when
- Adummy activities are large in number.
- Bevents happen as the schedule.
- Cthere is deficiency of resourcesCorrect
- Dthere is excess availability of resources
Solution
Concept
Slack is the difference between the latest allowable time and the earliest expected time for an event. A negative slack means the project is running behind schedule, which usually happens due to a shortage of resources.
Formula
Slack = TL - TE
Step-by-step solution
1. Understand the definition of slack in PERT: Slack = Latest Allowable Occurrence Time (TL) - Earliest Expected Occurrence Time (TE). 2. When TL is less than TE, slack becomes negative (Slack < 0). 3. Negative slack indicates that the event is delayed and will not meet the target completion date. 4. This delay occurs when activities take longer than planned, often caused by a deficiency or shortage of resources (like labor, machinery, or materials). Answer: (C) there is deficiency of resources
Explanation
Slack measures the spare time available for an event. Negative slack means the project is behind schedule and critical deadlines cannot be met with current progress. This delay is typically caused by a lack or deficiency of resources like men, money, and machinery.
Why the other options are wrong
A: Dummy activities represent logic and have zero time or resource, so their number does not cause negative slack. B: When events happen on schedule, slack is zero. D: Excess availability of resources speeds up the project and gives positive slack.
Shortcut
Negative slack = Project is behind schedule = Shortage or deficiency of resources.
Common mistake
Students often confuse negative slack with excess resources, but excess resources actually lead to positive slack (ahead of schedule).
Correct answer: C) there is deficiency of resources