The excess of minimum available time over activity time is called
- ATotal Float
- BIndependent FloatCorrect
- CFree Float
- DInterfering Float
Solution
Concept
Types of float in CPM network analysis
Formula
IF = Ej - Li - tij
Step-by-step solution
1. Recall CPM network float definitions: - Maximum available time = Lj - Ei. - Minimum available time = Ej - Li. 2. Independent Float (IF) is the excess of minimum available time over the activity duration (tij): IF = (Ej - Li) - tij. 3. Total float is Lj - Ei - tij, and Free float is Ej - Ei - tij. 4. Therefore, option B (Independent Float) matches the exact definition. Answer: B
Explanation
Independent Float is defined as the excess of minimum available time over the activity duration: IF = (Ej - Li - tij). It represents the amount of time an activity can be delayed without affecting the schedule of any preceding or succeeding activities in the CPM network.
Why the other options are wrong
A) Total Float is the excess of maximum available time over activity duration (Lj - Ei - tij). C) Free Float is the excess of available time when both events occur at earliest times (Ej - Ei - tij). D) Interfering Float is the difference between Total Float and Free Float.
Shortcut
Minimum available time - duration = Independent Float; Maximum available time - duration = Total Float.
Common mistake
Selecting Total Float (excess of maximum available time) or Free Float (delay without affecting subsequent earliest starts).
Correct answer: B) Independent Float