The optimistic, most likely and pessimistic time for an activity are 7 days, 15 days and 17 days respectively. The expected completion time (in days) of this activity is
- A12
- B14Correct
- C16
- D18
Solution
Concept
Expected activity duration in PERT
Formula
te = (to + 4·tm + tp) / 6
Step-by-step solution
1. Given estimates: - Optimistic time (to) = 7 days - Most likely time (tm) = 15 days - Pessimistic time (tp) = 17 days 2. Apply the PERT expected time formula: te = (to + 4·tm + tp) / 6 3. Compute numerator: 7 + 4(15) + 17 = 7 + 60 + 17 = 84. 4. Divide by 6: te = 84 / 6 = 14 days. 5. Therefore, option B (14 days) is correct. Answer: B
Explanation
In PERT analysis, the expected activity duration (te) follows a beta distribution and is calculated as te = (to + 4·tm + tp) / 6. Substituting to = 7 days, tm = 15 days, and tp = 17 days gives te = (7 + 4×15 + 17) / 6 = 84 / 6 = 14 days.
Why the other options are wrong
A) 12 is less than the expected value. C) 16 days overestimates the duration by over-weighting the pessimistic estimate. D) 18 days exceeds even the pessimistic duration.
Shortcut
te = (7 + 4×15 + 17) / 6 = 84 / 6 = 14.
Common mistake
Taking a simple arithmetic mean (7 + 15 + 17)/3 = 13 days instead of weighting the most likely time by 4 in the beta distribution.
Correct answer: B) 14