A critical activity has
- AMaximum float
- BZero floatCorrect
- CMinimum float
- DAverage float
Solution
Concept
Critical activity
Step-by-step solution
1. A critical activity has no float, so any delay delays the project.
Explanation
Critical = zero total float.
Why the other options are wrong
Other options are not correct.
Shortcut
Critical = 0 float.
Correct answer: B) Zero float