In resources levelling,
- Athe total duration of project is reduced
- Bthe total duration of project is increased
- Cthe uniform demand of resources is achievedCorrect
- Dthe cost of project is controlled
Solution
Concept
Resource Leveling
Formula
No standard mathematical formula exists for resource leveling, as it is a scheduling technique focused on resource allocation and smoothing.
Step-by-step solution
1. Identify the primary objective of resource leveling in project management, which is to smooth out peak resource demands across the timeline. 2. Match this goal with the correct option, which states that a uniform demand of resources is achieved (Option C).
Explanation
Resource leveling is a technique used in project management to smooth out peaks and valleys in resource usage. It aims to balance the workload over time so that the demand for resources remains consistent and uniform throughout the project.
Shortcut
Associate Level with Uniform. Resource leveling aims to flatten or smooth out peak demands to achieve a uniform demand for resources.
Common mistake
Many students confuse resource leveling with resource smoothing, assuming that resource leveling reduces the total project duration (Option A) rather than keeping project duration constant and smoothing out resource allocation. Others mistake it for cost control (Option D) or assume it always increases project duration (Option B) because non-critical activities are shifted within available floats.
Correct answer: C) the uniform demand of resources is achieved