Resource smoothening means
- AGradual increase in resources
- BComplete revamping of resources to suit the requirement
- COptimization and economical utilization of resources
- DAdjustment of resources to have the least variationsCorrect
Solution
Concept
Definition and objective of resource smoothening
Formula
NONE
Step-by-step solution
1. Resource management in project planning involves balancing resource demand with availability. 3. Therefore, option C is selected as the correct statement. Answer: D
Explanation
Resource smoothening is a resource management technique used when the project completion date is fixed and non-negotiable. It aims to adjust the schedule of non-critical activities within their available floats to reduce peak resource demand and achieve minimal variation over time. Therefore, option D correctly defines resource smoothening as adjusting resources to have the least variations.
Why the other options are wrong
A) Resource smoothening does not involve a gradual increase in resources. B) It does not require complete revamping of resources.
Shortcut
Resource Smoothening adjusts non-critical activities within float to minimize fluctuations without extending project duration.
Common mistake
Confusing resource smoothening with resource leveling or general optimization and selecting option C.
Correct answer: D) Adjustment of resources to have the least variations