Match the following lists:
| List-I | List-II |
|---|---|
| A.Resource management | 1.Getting the correct materials to the workface when needed |
| B.Manpower leveling | 2.Judicious allocation of the physical resources |
| C.Supply chain management | 3.Practical improvement of the allocation of labor resources |
Select the correct option using the code given below (A-B-C):
- A2 - 3 - 1Correct
- B3 - 1 - 2
- C1 - 3 - 2
- D1 - 2 - 3
Solution
Concept
Resource management allocates physical resources well. Manpower leveling smooths the labour use. Supply chain management brings the right materials to the site on time.
Step-by-step solution
1. Resource management means judicious (wise) allocation of physical resources, so A → 2. 2. Manpower leveling means practical improvement in the allocation of labour, so B → 3. 3. Supply chain management means getting the correct materials to the workface when needed, so C → 1. 4. The code is A-B-C = 2-3-1, which is option (A).
Explanation
Resource management is about using physical resources (men, machines, materials) wisely. Manpower leveling removes the peaks and valleys in labour demand to improve labour allocation. Supply chain management makes sure the right material reaches the work point at the right time.
Why the other options are wrong
(B) wrongly matches resource management with labour allocation and supply chain with physical resources. (C) wrongly matches resource management with material delivery. (D) wrongly matches manpower leveling with physical resources and supply chain with labour.
Common mistake
Mixing up resource management (all physical resources) with manpower leveling (labour only).
Correct answer: A) 2 - 3 - 1